Point estimates hide risk: why boards need ranges

A single number feels firm but rarely holds. On a fictional $120 million project it has a 1% chance. How a range changes the budget decision, and how to present one to a board.

By Mike Bouman, Quantil · November 4, 2026

Boards love a single number. It's clear, it fits in a budget line, and it feels like a commitment. The problem is what it leaves out.

A point estimate is one cost figure, such as the base estimate. A range estimate shows the spread of likely outcomes and how probable each one is. A single number says nothing about its chances of holding, and on most projects the honest answer would be: not great.

What a single number hides

Take the fictional Millbrook Connector, a road and bridge project estimated at $120 million. Every line in that estimate is a reasonable "most likely" value. Nobody cut corners. But once you simulate the uncertainty in each line, plus six known risks, the picture looks very different:

Budget optionAmount ($M)Chance of staying within budget
Point estimate120.01%
Point estimate + flat 10%132.033%
P50135.850%
P80143.480%

None of the individual lines in that $120 million was wrong. The total was. Skewed cost items have a habit of overrunning far more than they underrun, so their most likely values don't add up to the most likely total. Add the customary 10% on top, and the board still has a two-in-three chance of coming back for more money. Our guide on why a percentage on top is not a risk budget shows the same effect on two other projects.

And this isn't some exotic case. Across 258 transport projects, nine out of ten went over budget, with an average overrun of 28% (Flyvbjerg et al., 2003).

Why ranges lead to better decisions

A range does three things a single number cannot.

  1. It makes risk appetite a real choice. Picking P50 or P80 is a deliberate decision about how much overrun risk you accept. With a point estimate, that decision gets made by accident. P50, P80 and P90 explained helps you pick the level.
  2. It shows you where to act. A range comes with its drivers. In the Millbrook example, the bridge costs and the risk of poor ground at the foundations dominate, which makes a strong case for more site investigation before the budget is fixed.
  3. It protects your credibility. A board that approved "$136 million at 50% confidence, $143 million at 80%" won't be shocked when the bill lands at $139 million. A board that approved $120 million will be.

More and more governments ask for ranges. The Australian Government requires P50 and P90 estimates for larger projects seeking Commonwealth funding. In the Netherlands, the forecast for the national flood defense program was reported as a P50 of €18.4 billion within a range of €14.3 billion to €22.5 billion (Horvat & Partners, 2024).

How to present a range to a board

The usual pushback is practical: "We still need one number for the budget." Fair enough. The answer isn't to hide the range. It's to build the decision around it.

The board gets its single number, and the range becomes the reason behind it.

A practical tip. The first reaction to a range is usually a practical one: “so which number goes into the budget?” That’s a fair question from anyone responsible for delivery. It changes the moment the range is tied to a decision: a project budget at P50, a reserve up to P80 and clear triggers for escalation. Then the range feels like protection instead of uncertainty, and the question shifts from “why isn’t this one number?” to “what are we doing about the top drivers?”

When a point estimate is fine

For small, routine work with plenty of comparable history, a point estimate plus a factor-based allowance can do the job. The more unique, larger or earlier the project, the more a range is worth.

Frequently asked questions

Isn't a range just a way to ask for more money?

No. A range often shows that part of the allowance isn't needed yet. It also lets you hold reserve centrally instead of padding every single estimate.

How wide should a range be?

As wide as the evidence supports. Early on, ranges of minus 20% to plus 50% are common. They narrow as design and procurement move forward.